How long does a power-floated floor take to cure before use?
You can walk on it after 24 hours and allow light foot traffic within 2 – 3 days. Wait about 7 days before light vehicles and 28 days before heavy forklifts or full racking loads, so the concrete reaches its design strength. Keep the slab moist or under a curing compound for at least the first 7 days.
How do you prevent cracking?
We use a dry-shake hardener where traffic is heavy, cure the slab from day one, and saw-cut control joints within 24 hours at the right spacing so any cracking happens inside the joint. Good sub-base compaction, the correct concrete grade and no extra water in the mix matter just as much, and we check all of these before the pour.
What floor thickness do you recommend?
Usually 125mm (5 in) for homes, garages and light-duty floors, 150 – 200mm for warehouses and commercial floors, and up to 300mm (12 in) for heavy industrial loads. Your structural engineer sets the final figure, and we finish to whatever the design calls for.
What is the difference between power floating and an ordinary screed?
Power floating finishes the structural slab itself while it is still fresh, so the surface is part of the concrete. An ordinary screed is a separate layer laid later, which can crack, sound hollow or delaminate. A power-floated floor is flatter, denser and more durable. It usually costs less too, because there is no second layer.
Is power floating good for residential floors?
Yes. A power-floated house slab is smooth, level and ready for tiles, vinyl or wood. You can also seal it and use it as the final finish. It saves the cost of a separate screed.
Power float vs tiles: which is better?
Tiles look good but can crack, sound hollow and need their grout cleaned. A sealed or polished power-floated floor has no joints to fail, handles heavy loads and costs less per square metre. Many clients power float the slab and tile only some rooms.
How long does a typical job take?
The finishing happens on the day of the pour. Most jobs take 1 – 7 days, depending on the area, the number of pours and any hardener, polishing or epoxy work.
How much does power floating cost per square metre in Kenya?
Our power floating starts from Ksh 250 per sqm. Area, concrete grade, the finish you want, site access and location all move the price, so we confirm a fixed quote after a free site visit.
Do you supply the concrete?
No. We are finishing specialists. You or your main contractor supplies the concrete, either ready-mix or batched on site. We advise on grade, slump and pour timing so the finish comes out right.
Do you offer a warranty?
Yes. Every job comes with a written workmanship warranty, with the terms set out in your quotation.
What are your payment terms?
Companies get 30-day terms after completion, subject to approval. For individuals and smaller jobs we take a 50% deposit to book the crew, with the balance on completion. We accept M-Pesa and bank transfer.
Do you work outside Nairobi?
Yes. We work across Kenya, including Mombasa, Nakuru, Kisumu, Eldoret, Thika, Ruiru, Kitengela and Athi River. For sites outside Nairobi we quote mobilisation upfront.
Do you hire out power float machines?
No, our machines are not for hire on their own. Our ride-on and walk-behind floats always come with our trained operators, because the finish depends on timing and skill as much as on the machine.
No matching questions. Ask us on WhatsApp.
The power float cost guide
What drives the price per sqm, how to budget a warehouse or house slab, and 10 questions to ask any flooring contractor. We send it to your WhatsApp as a PDF.